Completed project

1 MW solar and 4.16 MWh battery storage for a leading religious organisation's new auditorium.

Toptech delivered a large scale hybrid renewable energy and energy storage solution for the new auditorium of a leading religious organisation, on the Lagos to Ibadan Expressway: approximately 1 MWp of solar PV, 4.16 MWh of battery storage and 800 kW of Deye hybrid inverter capacity, integrated to run on solar, battery, grid and generator power, from installation through to commissioning between July and November 2025.

1 MW solar and 4.16 MWh battery storage for a leading religious organisation's new auditorium.
Client
One of our clients (one of the leading religious organisations)
Standard
Hybrid solar, battery, grid and generator
Role
Solar PV, hybrid power, battery storage, electrical infrastructure, fire suppression, testing and commissioning
Scope
1.01 MWp solar PV, 800 kW Deye hybrid inverters, 4.16 MWh battery storage, ATS and distribution, earthing, power shelters, fire suppression, commissioning
Implementation timeline
Phase 01
Solar PV installation

1,709 x 590 W Jinko monocrystalline modules installed on the auditorium roof, with PV cabling and aggregation.

Phase 02
PV aggregation and shelters

Rooftop circuits consolidated through combiner boxes in two constructed power shelters.

Phase 03
Inverters and battery storage

800 kW of Deye hybrid inverters and about 4.16 MWh of 192 kWh battery units installed and integrated.

Phase 04
Electrical distribution and safety

ATS, distribution panels, cabling, earthing and fire suppression, tied into grid and generator supply.

Phase 05
Testing and commissioning

Reconfigured into two inverter groups with the Deye team and commissioned with a Deye licensed engineer.

Overview

Toptech delivered a large scale hybrid renewable energy and energy storage solution for the new auditorium of a leading religious organisation, along the Lagos to Ibadan Expressway.

The project involved the installation of approximately 1 MWp of solar PV capacity, supported by approximately 4.16 MWh of battery energy storage and 800 kW of Deye hybrid inverter capacity. The solar array comprised 1,709 units of 590 W Jinko monocrystalline PV modules, for a total installed capacity of approximately 1.009 MWp, and the inverter system consisted of 10 units of 80 kW Deye hybrid inverters. The system was designed and integrated to operate with both grid supply and generator power, providing a flexible hybrid power architecture for the facility.

  • •Approximately 1.01 MWp of solar PV: 1,709 x 590 W Jinko monocrystalline modules
  • •800 kW of Deye hybrid inverter capacity: 10 x 80 kW inverters
  • •Approximately 4.16 MWh of battery energy storage in 192 kWh units
  • •PV aggregation through combiner boxes in two power shelters
  • •Automatic transfer switching, distribution panels and power cabling
  • •Earthing and bonding across the PV, inverter and battery systems
  • •Power shelters constructed to house the electrical and storage equipment
  • •Fire suppression and security systems
  • •Integration with both utility grid and generator supply
  • •Testing and commissioning with a Deye licensed engineer

The problem

The New Auditorium is a large and energy intensive facility with critical electrical loads requiring dependable and well coordinated power infrastructure. The project therefore required more than simply installing solar panels: the renewable energy system had to be integrated with existing conventional power sources while providing adequate energy storage and reliable power conversion.

  • •Integration of multiple power sources: the hybrid system had to operate as part of an electrical infrastructure incorporating both utility grid and generator supply, with careful coordination of the inverters, automatic transfer switching, distribution and protection
  • •Synchronisation of the inverter system: the most significant technical challenge was that all ten 80 kW Deye inverters could not be synchronised to run the full 800 kW bank as a single group under the project configuration
  • •Large scale PV installation: 1,709 modules had to be installed and interconnected across the auditorium roof and aggregated through multiple combiner boxes
  • •Distributed power shelters: appropriately constructed shelters were needed, with PV and electrical connections routed from the rooftop array to the respective equipment
  • •Battery energy storage: approximately 4.16 MWh required careful positioning, interconnection, earthing and integration with the hybrid inverters
  • •Protection and safety: earthing, automatic transfer switching, distribution and fire suppression were required across the installation

The solution

Toptech implemented a comprehensive solar, battery storage and electrical integration solution, working in coordination with the Deye technical team.

Toptech installed 1,709 x 590 W Jinko monocrystalline modules on the auditorium roof, arranged to make best use of the available area, giving an installed capacity of about 1.01 MWp, with the associated PV cabling and aggregation. The rooftop arrays were consolidated through PV combiner boxes within the two power shelters, providing an organised interface between the large array and the power conversion equipment.

The ten 80 kW Deye inverters gave 800 kW of total capacity. Because the full bank could not be synchronised as one system, Toptech worked with the Deye technical team to reconfigure it into two independent inverter groups, six inverters serving the auditorium altar and four serving another designated load group, a practical and stable solution that retained the full installed capacity. The battery system, built from multiple 192 kWh units for about 4.16 MWh, was positioned, installed and integrated with the hybrid inverter infrastructure.

Toptech designed, constructed and installed the electrical distribution infrastructure to tie the renewable system into the facility: automatic transfer switches, distribution panels, cabling and containment, equipment connections, earthing and bonding, and the interconnections between the hybrid system and the facility, integrated with both grid and generator supply. Toptech also constructed and equipped the power shelters, implemented the earthing infrastructure, installed the fire suppression system around the battery and electrical equipment, and carried out testing and commissioning jointly with a Deye licensed engineer, after which the completed system was commissioned as an integrated hybrid power solution.

Project impact

The project demonstrates Toptech's capability to deliver large scale renewable energy and energy storage systems for complex facilities, combining 1.01 MWp of solar PV, 800 kW of Deye hybrid inverter capacity and 4.16 MWh of battery storage with grid and generator integration, ATS and distribution infrastructure, earthing and fire suppression.

Beyond the scale of the installation, the project demonstrated Toptech's ability to respond to complex technical challenges during commissioning and to develop a practical engineering solution in collaboration with the equipment manufacturer, executing the complete chain from solar PV installation and aggregation through inverters, battery storage, distribution, grid and generator integration, ATS, earthing and fire protection to testing and commissioning.

On site

8 photos

Outcomes & ROI

The project at a glance, delivered by Toptech between July and November 2025.

1.01 MWp
Solar PV installed

1,709 x 590 W Jinko monocrystalline modules on the auditorium roof

4.16 MWh
Battery storage

Built from multiple 192 kWh battery units

800 kW
Hybrid inverters

10 x 80 kW Deye, configured as groups of six and four

4
Power sources integrated

Solar, battery, grid and generator

End to end hybrid delivery

Solar PV, aggregation, inverters, battery storage, distribution, grid and generator integration, ATS, earthing, fire protection and commissioning as one scope.

A practical answer to a live problem

When the full 800 kW inverter bank could not be synchronised, Toptech reconfigured it into two stable inverter groups with the Deye team, retaining the full capacity.

Working with a global manufacturer

Delivered in coordination with the Deye technical team, and commissioned with a Deye licensed engineer.

Reporting method

Baselines are agreed before mobilisation and reported quarterly against uptime, efficiency and lifecycle cost.